CORNELL · SYSEN 5930 · FALL 2023

Give a service idea a plan you can question.

Bon Appétit proposed a different approach to food and grocery delivery. I contributed to the team’s project management plan and wrote the cost-management chapter, bringing scope, budget and progress into the same discussion.

Original work
Team 8 · Bon Appétit
My chapter
Part 5 · Cost Management Plan
This page’s experiment
Created in 2026 · fictional values
About 8 min read
100%

TEAM CONCEPT / DELIVERY & LOCAL COLLECTION

From individual doorsteps to local delivery points.

The team proposed fixed delivery points near communities, followed by a short collection trip for customers. The aim was to improve routes and reduce loss during delivery, with drones or unmanned vehicles considered as possible extensions.

Delivery routeFixed delivery pointLocal collection

This was a course proposal for a service and product. The team’s planning material covered labour rates, task durations, a time-phased budget and a schedule baseline, which informed my cost-management section.

MY CHAPTER / START WITH SCOPE AND BUDGET

Ask whether the budget supports the proposed work.

Part 5 identifies me as the author of the cost management plan. I first asked whether the original budget could cover software optimisation, delivery facilities and potential unmanned delivery. I then explicitly introduced a hypothetical expanded budget to discuss costs across the proposed phases.

  1. 01

    Start with scope

    What work and resources sit behind fixed delivery points, local collection and possible unmanned delivery? How much of that scope is the budget meant to cover?

  2. 02

    State the assumption

    My cost chapter questions the fit between the original budget and proposed scope, then explicitly introduces a hypothetical expanded budget for design, development and prototyping.

  3. 03

    Bring variance back to the work

    Compare planned work, completed work and actual spend at the same reporting point, then identify what needs investigation.

The chapter brings cost and schedule variance and earned-value measures into monitoring, with fortnightly reports and quarterly reviews. Its amounts, thresholds and budget expansion were coursework assumptions. Looking back, I would keep the habit of checking scope before interpreting the numbers.

FROM THE ORIGINAL TO AN EXPERIMENT / SEPARATE THE THREE VALUES

Spending less and delivering to plan are separate questions.

Earned value management (EVM) values completed work using its agreed budget, then compares it with the plan and actual cost. If spending is below plan, the next question is whether the work was delivered efficiently or simply has not been done yet.

The experiment below uses new fictional values to explore that distinction. Planned value PV, earned value EV and actual cost AC refer to the same reporting point; the graphic is a snapshot.

TRY THE COMPARISON / A 2026 METHOD DEMONSTRATION

Spent, delivered, planned: three different numbers.

These new fictional scenarios use a total budget of 100 units and cumulative values at one reporting point. EV weights completed work by its agreed budget, rather than by how much was spent.

First ask: which work is behind plan?

Planned work: 60 units. Completed work at budget: 30. Actual cost: 25.

Earned value needs reliable completion evidence. These ratios do not translate directly into days ahead or behind.

Cost variance CV
5
EV − AC

Completed work compared with what it cost.

Schedule variance SV
-30
EV − PV

Progress against planned work, in budget units, not days.

Cost performance CPI
1.20
EV ÷ AC

Budgeted work value delivered per unit spent.

Schedule performance SPI
0.50
EV ÷ PV

Completed work value relative to the plan at this point.

CV and SV: positive is favourable, negative unfavourable. CPI and SPI: above 1 is favourable, below 1 unfavourable. A zero denominator displays “—” because the ratio is undefined.

This demonstration compares one snapshot; actual cost can exceed the total budget. It does not forecast finish dates or final cost. Definitions & formulas: NSF EVM Gold Card (new tab) ↗

DECISION THEATRE / 02 · THE SEQUENCE BEFORE HANDOFF

Two days faster. Does delivery move too?

Seven activities turn a service idea into a handoff. Change the site or interface duration and inspect which chain determines the finish.

A fictional exercise authored in 2026, separate from the Bon Appétit schedule. Elapsed days start at zero. Dependencies are finish-to-start with no lag; resource limits are not modelled.

Current finish12days
Against baseline0days
Zero-float activities5/ 7
CRITICAL ACTIVITY

Prepare the service interface

Product and implementation · After: Agree scope and acceptance

Earliest start: day 2; finish: day 7. Total float: 0 days.

Total float is the room to move this activity without moving the current project finish. Float on connected activities cannot simply be added together.

Edit the seven durations

Full calculation: early, late and total float (days)
ActivityAfterDurationEarly startEarly finishLate startLate finishFloat
Agree scope and acceptancescope—202020
Prepare the service interfaceinterfacescope527270
Prepare the collection pointsitescope325472
Write operating instructionsbriefscope426593
Run joint acceptance teststestinterface / site279790
Rehearse the handoffrehearsetest / brief29119110
Confirm deliveryreleaserehearse1111211120
Method and three questions before handoff

Critical path method: a forward pass finds early dates, a backward pass finds late dates, and total float equals late start minus early start.

  1. Are you shortening the work that controls delivery, or work with existing float?
  2. Do independent activities still compete for the same person or equipment?
  3. After acceptance, does the next owner know who handles a failure?
Method reference: PMI critical-path calculations (new tab) ↗

KEEP THE CALL / LEAVE A VERSION OF THE DECISION

Keep the settings beside the reasoning.

Save the seven applied durations above. Crew count and priority order can be saved separately in the resource lab below. Unapplied inputs are excluded.

Restore a saved version of this tool (0)

Loading replaces this page’s settings and unapplied inputs. The original journal entry stays.

    No saved versions of this tool yet.

    Organise and compare in your reading space ↗

    RESOURCE LAB / THE SAME PLAN, FINITE CAPACITY

    The tasks can overlap. Can the people?

    Use the seven applied durations above. Each activity occupies one interchangeable crew for its full, uninterrupted duration. See whether limited capacity changes delivery, then adjust the scheduling order.

    Precedence-only lower bound12days
    Current priority schedule12days
    Shortest enumerated schedule12days

    The current schedule finishes 0 days above the precedence-only bound. Changing the priority order can recover 0 days in this model.

    Which activity gets a slot first?

    Move activities up or down while keeping predecessors ahead. This is the order of reserving feasible intervals, not a rule that activities must start one by one.

    1. 01Agree scope and acceptance
    2. 02Prepare the service interface
    3. 03Prepare the collection point
    4. 04Write operating instructions
    5. 05Run joint acceptance tests
    6. 06Rehearse the handoff
    7. 07Confirm delivery

    Occupied time and waiting

    Solid bars show occupied time. Dashed segments show waiting for capacity after predecessors finish. The full table below gives every value.

    One cell per day from day zero; each number is occupied crews, with capacity 2.

    Resource schedule (days); capacity waiting is not CPM total float
    ActivityDurationPredecessors readyStartFinishCapacity wait
    Agree scope and acceptance20020
    Prepare the service interface52270
    Prepare the collection point32250
    Write operating instructions42593
    Run joint acceptance tests27790
    Rehearse the handoff299110
    Confirm delivery11111120
    How is the shortest schedule found?

    The solver checks all 8 precedence-valid priority orders. For each, it reserves the earliest continuous interval after predecessors finish and within crew capacity, then compares finish times. 4 orders reach the shortest finish; they need not produce distinct schedules.

    This is a small exhaustive exercise: seven fixed-duration activities in whole days, no interruptions or holidays, and one interchangeable crew per activity. Skills, handoff costs and uncertainty in real projects require additional modelling.

    Method reading: schedule generation schemes (new tab) ↗

    KEEP THE CALL / LEAVE A VERSION OF THE DECISION

    Keep the settings beside the reasoning.

    Save a version of the applied settings only when you choose. Unapplied inputs are excluded. Restore or compare saved versions from the local journal.

    Restore a saved version of this tool (0)

    Loading replaces this page’s settings and unapplied inputs. The original journal entry stays.

      No saved versions of this tool yet.

      Organise and compare in your reading space ↗

      Try another time constraint: plan several fishing targets ↗

      LOOKING BACK IN 2026 / RETURN THE NUMBERS TO THE WORK

      After finding a variance, ask who acts on it.

      Reading the plan now, I would keep the measures beside the work breakdown: which deliverable is behind, why, who can fill the information gap, and when should it be reviewed again? Similar questions run through CUSD coordination and my later work on requirements and acceptance.

      ORIGINAL WORK & METHOD REFERENCES

      Read the experience, assumptions and new experiment in context.

      Team8_BonAppetit_SYSEN5930_Assignment5_Word
      Part 5 — Cost Management Plan, attributed to Jinglin “Ronaldo” Li. Project context and participation were also checked against the August 2026 CV. Original budget estimates are not presented as operating results.

      The retrospective and experiment were written in October 2026. The experiment uses budget units; its definitions and formulas were checked against the primary references below.

      AFTER READING / THE CONVERSATION

      What would you add?

      Account & reading space ↗

      Add an experience, ask a question or point out a correction. Both language editions share this article’s discussion.

      Public comments are not open yet. Keep a draft on this device, or send your thoughts through the contact page.

      Write a local draft

      Only “Save on this device” stores the draft. Clear it on shared devices; it is not published automatically.

      0 / 1600

      Send it through the contact page ↗

      Same moment / Different meridians

      A moment, shared.

      Your time, alongside mine.

      Your time

      — : —

      Waiting for the browser clock

      —

      Ronaldo’s time

      — : —

      Waiting for the browser clock

      Asia/Singapore

      Enable JavaScript to see local time and the time difference.

      The weather where you are

      Enable JavaScript for city and weather.

      IP location may point to a network exit. Device location can refine it.

      Your clock uses your browser; mine is set to Singapore. IP city and weather are cached in this browser session for 30 minutes. Device location needs permission; rounded coordinates are used for weather and aren’t saved by this site.

      IP · ipwhois.io ↗Weather · Open-Meteo ↗